Post by Admin on Oct 17, 2013 10:17:41 GMT -5
Board_Report Date: 09/17/2013 Seq: 1
ANNEX AND SITE WORK UPDATE
September 11, 2013
R.I.. will be doing the punch list on the building today.
D Energy has work ordered to change the transformer which the electrical for the building will be hooked to. Once the electrical is connected Dan F (the oversite engineer) will then be notified to walk through and compile a final check list if necessary.
If all goes well the final inspection will be called for.
The site work is also nearing completion. The sidewalks are done. The sod is ordered for the retention pond. Txxxxx will be removing the materials put in the planters in the parking lot so that organic soil can be put in as per the site plan instructions. The landscaper will plant the required live oaks, 1 in each planter. The landscaper will also begin planting the proposed landscaping around the building and sidewalks today.
En has called for the surveyors to come in and do the “as-builts". Txxxx will also be heating and re-rolling the parking lot to smooth out damage done by the concrete trucks.
En will do a walk through with Txxxxx and compile a punch list if necessary. If all goes well they will also be able to call for the final inspection.
|
|